The new Fuller Warren Bridge in Jacksonville, Florida, USA, is an eight-lane, 1.4-mile-long bridge across the St. Johns River. Part of the I-95 interstate system, the project was sponsored by the Florida Department of Transportation (FDOT).

One section of the new bridge was opened to traffic in April 2000 but it wasn’t until November 2002 that all eight lanes were fully opened.

BRIDGE STRUCTURE

The bridge is eight lanes wide, four in each direction, and 1.4 miles long. It can carry approx. 100,000 vehicles per day.

The new bridge replaced the Fuller Warren Bascule Bridge which had a substandard roadway width, required frequent repairs and was one of two stop conditions remaining on this major north-south expressway. The Fuller Warren Bascule Bridge was opened in 1954. It was a four-lane structure with no emergency lanes.

The study for the new project was carried out in 1990 and the final design contract was awarded in 1992 to HNTB Corporation.

CHARACTERISTICS AND COST

The overall cost of the project was around $100 million.

The replacement bridge structure consists of 52 spans totalling more than 7,500ft. The main span over the shipping channel is 250ft with a vertical clearance of 75ft.

The new bridge provides three lanes in each direction for the I-95 and an auxiliary lane in each direction for traffic to enter or exit the I-95. Four, 10ft shoulders are provided.

Approach spans, with a few exceptions, are 140ft long and use 78ft modified bulb tee beams made continuous for live load. At the east end of the project an existing bridge over the FEC railroad, constructed with steel beams, was widened.

ELASTOMERIC BEARING PADS

Elastomeric bearing pads were used throughout the project except at the three-span channel unit where pot bearings were installed. Seismic continuity between the super and sub-structure is provided by 1ft 6in-diameter dowels cast into and projecting out of the top of the pier caps. The projecting dowels reside inside 8ft x 4ft structural tube sections cast into the bottom surface of end diaphragms.

HAMMERHEAD TYPE PIERS

The superstructure is supported by hammerhead type piers founded on 36ft, 48ft or 72ft diameter drilled shafts. The land pier columns are cast-in-place. The river pier columns and all of the beams on the project were precast at a yard set up.

CHANNEL UNIT

The 650ft channel unit is three continuous spans (200ft, 250ft, 200ft) made of 3ft to 80ft-deep modified bulb tee segments and two haunched pier segments. The haunched pier segments transition from 120ft deep at the piers to 80ft deep at the ends.

ERECTION METHOD

The erection method used for the channel unit called for a temporary support system using temporary piers to support the haunched pier segments and ‘strongbacks’ to support the end segments and centre segments (drop-in-beams).

The project was architecturally enhanced by understating pier cap strength with post-tensioning, using buttresses and copings at pier cap to column connections, shaping pier columns using octagonal shapes and rustication, and finally by coating all viewable concrete surfaces.

LEAD CONTRACTORS

HNTB Corporation designed the bridge. Balfour Beatty Construction, Inc. was the lead contractor. Parsons Brinckerhoff CS, Inc. provided construction inspection services. Balfour Beatty also demolished the old four-lane bridge.